Changes between Version 5 and Version 6 of docs/CommissioningPlan/P1.1
- Timestamp:
- 01/28/21 15:41:16 (4 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan/P1.1
v5 v6 12 12 **Procedure** 13 13 • Visually inspect if all the SHARK-NIR containers and boxes at the LBT mountain bay are safe and secure. 14 * Inspection of the state of tilt and shock sensor. 14 15 • Check if there is any damage to any part of the shipment. If yes, note them, take photos, and communicate to the respective insurance party (if needed). 15 16 **Success criteria** 16 17 • No damage to any container or boxes. 18 * No shock sensors activated. 17 19 **Notes** 18 20 … … 25 27 26 28 **Comments** 27 LM: I would add in the Procedure an inspection of the state of tilt and shock sensor and in the success criteria that these sensors must not be activated. 29 LM: I would add in the Procedure an inspection of the state of tilt and shock sensor and in the success criteria that these sensors must not be activated. [DONE]