wiki:docs/CommissioningPlan/P1.1

Version 5 (modified by lmarafatto, 4 years ago) (diff)

--

P1.1 Inspection of the boxes

  • Phase : 1
  • Status : Draft
  • Category : Unpack, Assemble, Verification, and Installation (C1)
  • Recurrence : once (when SHARK-NIR reaches LBT)
  • Duration : half a day

Description

  • Visual inspection of all the SHARK-NIR containers and boxes at the LBT mountain bay

Prerequisites

  • All the SHARK-NIR containers and boxes should be at LBT mountain bay

Procedure

  • Visually inspect if all the SHARK-NIR containers and boxes at the LBT mountain bay are safe and secure.
  • Check if there is any damage to any part of the shipment. If yes, note them, take photos, and communicate to the respective insurance party (if needed).

Success criteria

  • No damage to any container or boxes.

Notes

LBTO support

  • Crane operator to lift and move stuff.
  • 1-2 crew to support moving containers/boxes.

Associated SHARK-NIR personnel

Date performed and by whom

Comments LM: I would add in the Procedure an inspection of the state of tilt and shock sensor and in the success criteria that these sensors must not be activated.