P1.1 Inspection of the boxes
- Phase : 1
- Status : Draft
- Category : Unpack, Assemble, Verification, and Installation (C1)
- Recurrence : once (when SHARK-NIR reaches LBT)
- Duration : half a day
Description
- Visual inspection of all the SHARK-NIR containers and boxes at the LBT mountain bay
Prerequisites
- All the SHARK-NIR containers and boxes should be at LBT mountain bay
Procedure
- Visually inspect if all the SHARK-NIR containers and boxes at the LBT mountain bay are safe and secure.
- Check if there is any damage to any part of the shipment. If yes, note them, take photos, and communicate to the respective insurance party (if needed).
Success criteria
- No damage to any container or boxes.
Notes
LBTO support
- Crane operator to lift and move stuff.
- 1-2 crew to support moving containers/boxes.
Associated SHARK-NIR personnel
Date performed and by whom
Comments LM: I would add in the Procedure an inspection of the state of tilt and shock sensor and in the success criteria that these sensors must not be activated.