    11== P1.12 Testing of SCICAM image grabbing by SOUL-AO ==
    2 •       **Phase**               :       1 
    3 •       **Status**              :       Draft
    4 •       **Category**            :       Unpack, Assemble, and Verification (C1)
    5 •       **Recurrence**  :       once
    6 •       **Duration**            :       2 days
     2
     3- **Phase**             :       1 
     4- **Status**            :       Draft
     5- **Category**  :       Daytime testing (functionality and operability) (C3)
     6- **Recurrence**        :       once
     7- **Duration**  :       2 days
     8
    79**Description**
    8 •       Testing the SCICAM imaging grabbing (from a repository/folder) by SOUL-AO which is a pre-requisite for the SOUL-AO optimization for SHARK-NIR
     10- Testing the SCICAM imaging grabbing (from a repository/folder) by SOUL-AO which is a pre-requisite for the SOUL-AO optimization for SHARK-NIR.
     11
    912**Prerequisites**
    10 •       ICE compatibility between SHARK-NIR and SOUL-AO system
    11 * SCICAM image should have a header following FITS standard
     13- ICE compatibility between SHARK-NIR and SOUL-AO system
     14- SCICAM image should have a header following FITS standard
     15
    1216**Procedure**
    13 •       Save a SCICAM image (with a PSF image) on the agreed folder or repository
    14 •       Check if SOUL-AO can grab the image and analyze the PSF
     17- Save a SCICAM image (with a PSF image) on the agreed folder or repository
     18- Check if SOUL-AO can grab the image and analyze the PSF
     19
     20**Templates**
     21
    1522**Success criteria**
    16 •       SOUL-AO SW can grab the SCICAM image
     23- SOUL-AO SW can grab the SCICAM image
     24
    1725**Notes**
    18 The time dedicated to this activity has to be considered in combination with the other activities if needed. Parallelism is possible.
    19 * Points of contact: Alfio and Fabio from Arcetri
     26- The time dedicated to this activity has to be considered in combination with the other activities if needed. Parallelism is possible.
     27- Points of contact: Alfio and Fabio from Arcetri
    2028
    2129**LBTO support**
    22 * Liquid Nitrogen refill is required in the cleanroom.
    23 * LBTO SW support may be required
    24 
    25 **Associated SHARK-NIR personnel**
     30- Liquid Nitrogen refill is required in the cleanroom.
     31- LBTO SW support may be required
    2632