    v14 v15  
    1 == P1.8 Instrument re-alignment ==
     1== P1.11        Instrument re-alignment ==
    22
    33- **Phase**             :       1 
     
    1111
    1212**Prerequisites**
    13 - SHARK-NIR connected to LBT network.
     13- SHARK-NIR is connected to the LBT network.
    1414- Electronics cabinets on.
    1515- The cryostat should be running and cooled down.