Changes between Version 14 and Version 15 of docs/CommissioningPlan/P1.11
- Timestamp:
- 04/22/22 18:32:50 (3 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan/P1.11
v14 v15 1 == P1. 8Instrument re-alignment ==1 == P1.11 Instrument re-alignment == 2 2 3 3 - **Phase** : 1 … … 11 11 12 12 **Prerequisites** 13 - SHARK-NIR connected toLBT network.13 - SHARK-NIR is connected to the LBT network. 14 14 - Electronics cabinets on. 15 15 - The cryostat should be running and cooled down.