wiki:docs/CommissioningPlan/P1.11

Version 15 (modified by kradhakrishnan, 3 years ago) (diff)

--

P1.11 Instrument re-alignment

  • Phase : 1
  • Status : Draft
  • Category : Unpack, Assemble, and Verification (C1)
  • Recurrence : once
  • Duration : 1-6 days

Description

  • In case, the internal alignment verification (P1.10) points in the direction of misalignments, the SHARK-NIR needs to be re-aligned.

Prerequisites

  • SHARK-NIR is connected to the LBT network.
  • Electronics cabinets on.
  • The cryostat should be running and cooled down.
  • Access to the clean tent.

Procedure

  • TBW

Templates

Success criteria

  • Perform P1.10 again after the re-alignment, and make sure the optical quality is within specifications.

Notes

  • The actual number of days for this activity cannot be specified at this point. It could be between 1 day to a maximum of 6 days (TBC).

LBTO support

  • Liquid Nitrogen refill is required in the cleanroom.
  • We will need lights ON and OFF during the re-alignment of the instrument inside the cleanroom.
  • 4D interferometer (TBC).
  • Access to the clean tent.

Date performed and by whom