P1.11 Instrument re-alignment
- Phase : 1
- Status : Draft
- Category : Unpack, Assemble, and Verification (C1)
- Recurrence : once
- Duration : 1-6 days
Description
- In case, the internal alignment verification (P1.10) points in the direction of misalignments, the SHARK-NIR needs to be re-aligned.
Prerequisites
- SHARK-NIR is connected to the LBT network.
- Electronics cabinets on.
- The cryostat should be running and cooled down.
- Access to the clean tent.
Procedure
- TBW
Templates
Success criteria
- Perform P1.10 again after the re-alignment, and make sure the optical quality is within specifications.
Notes
- The actual number of days for this activity cannot be specified at this point. It could be between 1 day to a maximum of 6 days (TBC).
LBTO support
- Liquid Nitrogen refill is required in the cleanroom.
- We will need lights ON and OFF during the re-alignment of the instrument inside the cleanroom.
- 4D interferometer (TBC).
- Access to the clean tent.
Date performed and by whom