145 | | '''SHARK-NIR Location''': LBT platform. Some of the activities may run in parallel. All daytime activities. |
146 | | ||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (days)'''||'''Category'''|| |
147 | | ||P2.0A||[wiki:/docs/CommissioningPlan/P2.0A Installation of SHARK-NIR on LBT platform]||Day||2(preparation) + 2(lift-off) + 1(contingency)||C2|| |
148 | | ||P2.0B||[wiki:/docs/CommissioningPlan/P2.0B Installation of SHARK-NIR electronics on LBT platform]||Day||2||C2|| |
149 | | ||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Basic functionality and shutdown procedure test, cryostat cooldown]||Day||1||C3|| |
150 | | ||P2.2||[wiki:/docs/CommissioningPlan/P2.2 Instrument operability and functioning]||Day||2||C3|| |
151 | | ||P2.3||[wiki:/docs/CommissioningPlan/P2.3 TCS communication test]||Day||2||C3|| |
152 | | ||P2.4||[wiki:/docs/CommissioningPlan/P2.4 SHARK-NIR alignment to the telescope]||Day||3||C3|| |
153 | | ||P2.5||[wiki:/docs/CommissioningPlan/P2.5 SOUL AO system test]||Day||5||C3 + C4|| |
154 | | ||P2.6||[wiki:/docs/CommissioningPlan/P2.6 NCPA measurements]||Day||8||C3 + C4|| |
155 | | ||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Star center Fourier mode images]||Day||2||C3|| |
156 | | ||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Checking pointing offset between SHARK-NIR and SOUL-AO]||Day||1||C3 + C4|| |
157 | | ||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Science detector calibrations (on the telescope)]||Day||1||C3 + C4|| |
158 | | ||P2.10||[wiki:/docs/CommissioningPlan/P2.10 Cryostat warm up check]||Day||2||C3|| |
159 | | ||Total||(4 days of) contingency (15%) included within || ||34 days || || |
160 | | |
161 | | |
162 | | === Phase 3 (Commissioning)=== |
163 | | '''SHARK-NIR Location''': LBT platform. All nighttime activities. Some daytime support (within SHARK-NIR) is anticipated. Also, the SHARK-NIR software, SHINS, is expected to be almost ready to be tested. |
| 147 | '''SHARK-NIR Location''': LBT platform. Some of the activities may run in parallel. All activities are __daytime__. |
| 148 | |
| 149 | **__Pre-Com-Run-2__** |
| 150 | ||'''Number'''||'''Activity Name'''||'''Duration (days)'''||'''Category'''||'''Note'''|| |
| 151 | ||P2.0A||[wiki:/docs/CommissioningPlan/P2.0A Installation of SHARK-NIR on LBT platform]||6||C2|| || |
| 152 | ||P2.0B||[wiki:/docs/CommissioningPlan/P2.0B Installation of SHARK-NIR electronics on LBT platform]||2||C2|| || |
| 153 | ||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Basic functionality and shutdown procedure test, cryostat cooldown]||1||C3|| || |
| 154 | ||P2.2||[wiki:/docs/CommissioningPlan/P2.2 Instrument operability and functioning]||1||C3|| || |
| 155 | ||P2.3||[wiki:/docs/CommissioningPlan/P2.3 TCS communication test]||2||C3||Although 2 days of work is required, a lot cango in parallel with other ones. For the estimation of total days, we consider 1 day. || |
| 156 | ||P2.4||[wiki:/docs/CommissioningPlan/P2.4 SHARK-NIR alignment to the telescope]||3||C3|| || |
| 157 | || || Total without contingency||14 days || |
| 158 | || || Total with 10% contingency||**15.5 days** || |
| 159 | |
| 160 | **__Pre-Com-Run-3__** |
| 161 | ||'''Number'''||'''Activity Name'''||'''Duration (days)'''||'''Category'''||'''Note'''|| |
| 162 | ||P2.5||[wiki:/docs/CommissioningPlan/P2.5 Cryostat Cooldown and Science detector calibrations]||1||C3 + C4|| || |
| 163 | ||P2.6||[wiki:/docs/CommissioningPlan/P2.6 SHARK-NIR system level characterization at different telescope elevations]||6||C3 + C4||Checking pointing offset between SHARK-NIR, LBTI, and SOUL-AO, SOUL-AO tests, and NCPA measurements.|| |
| 164 | ||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Star center Fourier mode images]||0.5||C3|| || |
| 165 | ||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Verification of the mask centering algorithm and final contrast with SOUL-AO and turbulence at ASM]||3||C3 + C4|| || |
| 166 | || || Total without contingency||10.5 days || |
| 167 | || || Total with 10% contingency||**11.5 days** || |
| 168 | |
| 169 | === Phase 3 (Commissioning & Science Verification)=== |