P3.8 Estimate the limiting magnitude for every filter
- Phase : 3
- Status : Draft
- Category : Nighttime testing (functionality and operability) (C4)
- Recurrence : once at commissioning
- Duration : 50 minutes
Description
- Limiting magnitude is verified for each scientific filter, with the LBTI AO running.
Prerequisites
- Atmospheric conditions: photometric.
- Authorize SHARK-NIR on the SX side.
- Photometric stars as targets for every filter.
- AO working.
Procedure
- Take unsaturated images of the photometric star for every science filter.
- Estimate the instrument throughput for every filter.
Success criteria
- xxx
Notes LBTO support Associated SHARK-NIR personnel
- JF, LM, MdP, MM (from AZ), DV?
Date performed and by whom