    1  == P3.6        PSF Alignment ==
    2 •       **Phase**               :       3 
    3 •       **Status**              :       Draft   
    4 •       **Category**            :       Nighttime testing (functionality and operability) (C5) + Nighttime calibration (C6)
    5 •       **Recurrence**  :       before every observing target (CI, LSS), starting from commissioning.
    6 •       **Duration**            :       2 hours
     1== P3.6 Verify the ADC rotation on sky ==
     2 
     3- **Phase**             :       3 
     4- **Status**            :       Draft   
     5- **Category**  :       Nighttime testing (functionality and operability) (C5)
     6- **Recurrence**        :       once at commissioning
     7- **Duration**  :       1 night
     8
    79**Description**
    8 •       Alignment of the PSF with occulter (or slit) in coronagraphic mode.
     10- Evaluate the performance of the SHARK-NIR ADC.
     11
    912**Prerequisites**
    10 •       Bad pixel map, Background or Dark, Flat-field, detector RON
     13- Atmospheric conditions: photometric.
     14- Authorize SHARK-NIR on the SX side.
     15- Photometric stars as targets for every filter.
     16- AO is working.
     17- Target(s) at different Zenith distances?
     18
    1119**Procedure**
    12 •       The position of the internal deformable mirror (TTM_DM) is optimized in order to have the PSF image on the intermediate focal plane centered with the occulter. This is obtained comparing the PSF image, formed on the SCICAM, with the image of the occulter, obtained on the SCICAM using the calibration flat-field source.
     20- Check the working of the ADC using different targets in varying zenith distances and observing using different science filters?
     21
     22**Templates**
     23
    1324**Success criteria**
    14 •       the expected accuracy of 0.2 pixels (DV: need to check if we can reach this).
     25- xxx
     26
    1527**Notes**
    16 •       Same as activity 8.3 in AD4
    17 * 7 cases, 30 mins per case.
     28
    1829**LBTO support**
    19 •       AO support
    20 **Associated SHARK-NIR personnel**
     30- AO support
    2131
    2232**Date performed and by whom**