Changes between Version 7 and Version 8 of docs/CommissioningPlan/P3.5
- Timestamp:
- 02/19/21 09:48:18 (4 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan/P3.5
v7 v8 4 4 • **Category** : Nighttime testing (functionality and operability) (C5) + Nighttime calibration (C6) 5 5 • **Recurrence** : before every observing target (CI, LSS), starting from commissioning. 6 • **Duration** : 1 night6 • **Duration** : 4 hours 7 7 **Description** 8 8 • Adjust the orientation of the coronagraphic masks with respect to the true orientation of the M2 spider by rotating the SHARK-NIR derotator.