Changes between Version 7 and Version 8 of docs/CommissioningPlan/P3.5


Ignore:
Timestamp:
02/19/21 09:48:18 (4 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan/P3.5

    v7 v8  
    44•       **Category**            :       Nighttime testing (functionality and operability) (C5) + Nighttime calibration (C6)
    55•       **Recurrence**  :       before every observing target (CI, LSS), starting from commissioning.
    6 •       **Duration**            :       1 night
     6•       **Duration**            :       4 hours
    77**Description**
    88•       Adjust the orientation of the coronagraphic masks with respect to the true orientation of the M2 spider by rotating the SHARK-NIR derotator.