P2.5 SOUL-AO verification

  • Phase : 2
  • Status : Draft
  • Category : Daytime testing (functionality and operability) (C2)
  • Recurrence : after instrument installation at telescope platform
  • Duration : 3 hours

Description

  • Proper working and tuning of the SOUL-AO parameters is verified. If any minor adjustments are required, they are either implemented immediately or marked for a later daytime work.

Prerequisites

  • Activities P1.9and P2.5 are successfully completed.

Procedure

  • AO veririfaction procedure comes here ?

Success criteria

  • SOUL AO system working in tandem with the SHARK-NIR system.
  • Acceptable improvement of the on-axis PSF for a given seeing and brightness of the star.

Notes

LBTO support Support on running SOUL-AO

Associated SHARK-NIR personnel

Date performed and by whom