Changes between Version 1 and Version 2 of docs/CommissioningPlan/P3.3


Ignore:
Timestamp:
01/19/21 14:16:23 (4 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan/P3.3

    v1 v2  
    1  == P3.3        Telescope control – telescope mode and offset ==
    2 •       **Phase**               :       3 
     1== P2.5 SOUL-AO verification ==
     2•       **Phase**               :       2 
    33•       **Status**              :       Draft   
    4 •       **Category**            :       Nighttime testing (functionality and operability) (C4)
    5 •       **Recurrence**  :       once at commissioning
    6 •       **Duration**            :       30 minutes
     4•       **Category**            :       Daytime testing (functionality and operability) (C2)   
     5•       **Recurrence**  :       after instrument installation at telescope platform
     6•       **Duration**            :       3 hours
    77**Description**
    8 •       For the correct telescope mode for SHARK-NIR find the offset direction and magnitude.
     8•       Proper working and tuning of the SOUL-AO parameters is verified. If any minor adjustments are required, they are either implemented immediately or marked for a later daytime work.
     9
    910**Prerequisites**
    10 •       Atmospheric conditions: should be able to see bight stars on the sky (preferably close to zenith?).
    11 •       Authorize SHARK-NIR on the SX side.
    12 •       Target maybe a pair of stars (not too bright) separated by ca. 1arcmin (known value)
     11
     12* Activities [wiki:/docs/CommissioningPlan/P1.9 P1.9]and [wiki:/docs/CommissioningPlan/P2.5 P2.5] are successfully completed.
     13
     14
    1315**Procedure**
    14 •       Send preset to the telescope.
    15 •       Center one of the stars to the central pixel of SCICAM.
    16 •       Issue the right offset to get the other star at the same pixel in SCICAM.
    17 •       Return to the original star and verify the centering.
     16•       AO veririfaction procedure comes here ?
     17
    1818**Success criteria**
    19 •       The offsets produce telescope motions of the size and (particularly) direction expected.
     19•       SOUL AO system working in tandem with the SHARK-NIR system.
     20•       Acceptable improvement of the on-axis PSF for a given seeing and brightness of the star.
     21
    2022**Notes**
    21 •       Steve Allenson can create a paddle for SHARK-NIR offset if this info is given to him.
     23
    2224**LBTO support**
    23 •       Support from LBTI/LBTO?
    24 •       Presence of John Hill usually helps while collimating for the first time.
    25 •       Steve Allenson (as the TO) will be a great asset too.
     25Support on running SOUL-AO
     26
    2627**Associated SHARK-NIR personnel**
    27 •       JF, LM, MdP, MM (from AZ),
     28
     29
    2830**Date performed and by whom**