Changes between Version 1 and Version 2 of docs/CommissioningPlan/P3.27


Ignore:
Timestamp:
04/23/22 20:48:26 (3 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan/P3.27

    v1 v2  
    1  == P3.27 Spectral resolution ==
    2 •       **Phase**               :       3 
    3 •       **Status**              :       Draft   
    4 •       **Category**            :       Daytime calibration (C3)
    5 •       **Recurrence**  :       once every month starting from commissioning.
    6 •       **Duration**            :       10 minutes
    7 **Description**
    8 •       Measure the spectral resolution for the LSS observing mode.
    9 **Prerequisites**
    10 •       Bad pixel map, Background frames
    11 **Procedure**
    12 •       This calibration is performed illuminating the slit with the instrument spectral calibration lamps with known characteristics (5 emission lines). A background with lamps switched off is required.
    13 **Success criteria**
    14 •       Accuracy of MRS: 0.5nm at 1.2 micron, LRS: 2 nm at 1.2 micron.
    15 **Notes**
    16 •       Same as activity 9.4 in AD4
    17 **LBTO support**
    18 •       Support from LBTI/LBTO?
    19 **Associated SHARK-NIR personnel**
    20 •       JF, LM, MdP
    21 **Date performed and by whom**