     1 == P3.27 Spectral resolution ==
     2•       **Phase**               :       3 
     3•       **Status**              :       Draft   
     4•       **Category**            :       Daytime calibration (C3)
     5•       **Recurrence**  :       once every month starting from commissioning.
     6•       **Duration**            :       10 minutes
     7**Description**
     8•       Measure the spectral resolution for the LSS observing mode.
     9**Prerequisites**
     10•       Bad pixel map, Background frames
     11**Procedure**
     12•       This calibration is performed illuminating the slit with the instrument spectral calibration lamps with known characteristics (5 emission lines). A background with lamps switched off is required.
     13**Success criteria**
     14•       Accuracy of MRS: 0.5nm at 1.2 micron, LRS: 2 nm at 1.2 micron.
     15**Notes**
     16•       Same as activity 9.4 in AD4
     17**LBTO support**
     18•       Support from LBTI/LBTO?
     19**Associated SHARK-NIR personnel**
     20•       JF, LM, MdP
     21**Date performed and by whom**