wiki:docs/CommissioningPlan/P3.21

Version 1 (modified by kradhakrishnan, 5 years ago) (diff)

--

P3.21 Star center

  • Phase : 3
  • Status : Draft
  • Category : Nighttime calibration (C5)
  • Recurrence : on every target, starting from commissioning.
  • Duration : 20 minutes

Description

  • This calibration is performed to calibrate the target star center with respect to the detector in order to provide a reference input for frame derotation and quadrant combination.

Prerequisites

  • Authorize SHARK-NIR on the SX side.
  • Atmospheric conditions: AO working conditions.
  • Bad pixel map, Dark

Procedure

  • DM produce a pattern offset with four spots symmetric with respect to the star + AO closed-loop + coronagraph
  • The required specifications of the corresponding image are a grid of at least 2x2 regularly spaced focal plane image peaks within 5 and 15 lambda/D with FWHM < 45 mas and separation precision < 6 mas.
  • DM offset applied on target acquisition to produce a waffle image. Find the center of the four first-order diffraction peaks (cross geometry) to deduce the pixel corresponding to the center field.

Success criteria

  • Accuracy of 3 mas (goal 1 mas)

Notes

  • Same as activity 7.8 in AD4

LBTO support

  • Support from LBTI/LBTO?

Associated SHARK-NIR personnel

  • JF, LM, MdP

Date performed and by whom