P3.18 Point the slit

  • Phase : 3
  • Status : Draft
  • Category : Nighttime testing (functionality and operability) (C5)
  • Recurrence : once at commissioning
  • Duration : 8 hours

Description

  • This activity will point the long slit at the (known) position angle of an off-axis source.

Prerequisites

  • Atmospheric conditions: AO working conditions.
  • Authorize SHARK-NIR on the SX side.
  • Have a list of binary systems with separations larger than the slits occulters (i.e. 100 and 200mas), possibly bright objects

Procedure

  • Preset to one of the stars in the binary system
  • Center the star on the slit
  • By moving the instrument derotator, point the slit at the nominal (known) position of the companion.

Templates

  • SHARKNIR_gen_tec_PSFAlignment

Success criteria

  • xxx

Notes

LBTO support

  • AO support

Date performed and by whom