Version 12 (modified by dvassall, 15 months ago) (diff) |
---|
P3.18 Point the slit
- Phase : 3
- Status : Draft
- Category : Nighttime testing (functionality and operability) (C5)
- Recurrence : once at commissioning
- Duration : 8 hours
Description
- This activity will point the long slit to the (known) position angle of an off-axis source.
Prerequisites
- Atmospheric conditions: AO working conditions.
- Authorize SHARK-NIR on the SX side.
- Have a list of binary systems with separations larger than the slits occulters (i.e. 100 and 200mas), possibly bright objects
Procedure
- Preset to one of the stars in the binary system
- Center the star on the slit
- By moving the instrument derotator, point the slit at the nominal (known) position of the companion.
Templates
- SHARKNIR_gen_tec_PSFAlignment
Success criteria
- xxx
Notes
LBTO support
- AO support
Date performed and by whom