     1 == P3.12       Checking field-stabilized mode/bearing rotation service ==
     2•       **Phase**               :       3 
     3•       **Status**              :       Draft   
     4•       **Category**            :       Nighttime testing (functionality and operability) (C4)
     5•       **Recurrence**  :       once at commissioning
     6•       **Duration**            :       40 minutes
     7**Description**
     8•       The field stabilized mode or in other words, the working of the bearing tracking service will be tested.
     9**Prerequisites**
     10•       Atmospheric conditions: AO working conditions.
     11•       Authorize SHARK-NIR on the SX side.
     12•       Targets (star cluster) near zenith and horizon (say airmass of 2).
     13**Procedure**
     14•       Select the target near airmass 2. There should be stars spread across the entire SCICAM, preferably close to the edges as well.
     15•       Start the bearing tracking services (field-stabilized mode).
     16•       Take short-exposure images for a duration of ##minutes.
     17•       Check if the positions of these stars.
     18•       Repeat the same for the target close to the zenith.
     19•       The above may be repeated for a target where the rotation of the bearing is in the opposite direction as of the above tested one.
     20**Success criteria**
     21•       The bearing tracking service works well and the field is stabilized within the precision needed.
     22**Notes**
     23**LBTO support**
     24•       Support from LBTI/LBTO?
     25**Associated SHARK-NIR personnel**
     26•       JF, LM, MdP
     27**Date performed and by whom**