  • docs/CommissioningPlan/P2.9

    v3 v4  
    88•       This activity corresponds to the flexure tests for the SHARK-NIR.
    99**Prerequisites**
    10 •       If relevant, estimate and remove the NCPA using phase-diversity method.
     10•       If relevant, estimate and remove the NCPA using the phase-diversity method.
    1111•       RR mounted on SX side.
    1212**Procedure**
     
    2222•       If the test results are not satisfactory, this activity may be repeated again after making proper countermeasures to reduce the flexure.
    2323**LBTO support**
    24 * Authorize SHARK-NIR on SX side.
     24* Authorize SHARK-NIR on the SX side.
    2525* RR will be required on the SX side.
    2626* Support from LBT SW Team, LBTI/Arcetri team to run SOUL AO