P2.9 Flexure tests
- Phase : 2
- Status : Draft
- Category : Daytime testing (functionality and operability) (C2)
- Recurrence : once at commissioning
- Duration : 3 days
Description
- This activity corresponds to the flexure tests for the SHARK-NIR.
Prerequisites
- If relevant, estimate and remove the NCPA using the phase-diversity method.
- RR mounted on SX side.
Procedure
- Test the positions of the various opto-mechanical components within the instrument using optical feedback while moving the telescope in elevation.
- Change the velocity and acceleration of the movement of the telescope in elevation if required.
- Remember to perform the tests for all the observing modes (whatever possible with RR or internal light sources)
- You may want to disentangle the flexure of the RR while moving the telescope in elevation by comparing the optical feedback for the same movement with the internal light source.
- This test will also test the working of the LBTO AO system while the telescope is moving in elevation.
- Compare the results with that of Padova flexure tests.
Success criteria
- All the images and data are saved for analysis or to create the lookup table.
Notes
- If the test results are not satisfactory, this activity may be repeated again after making proper countermeasures to reduce the flexure.
LBTO support
- Authorize SHARK-NIR on the SX side.
- RR will be required on the SX side.
- Support from LBT SW Team, LBTI/Arcetri team to run SOUL AO
Associated SHARK-NIR personnel
Date performed and by whom