Changes between Initial Version and Version 1 of docs/CommissioningPlan/P2.8


Ignore:
Timestamp:
03/05/20 12:31:30 (5 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan/P2.8

    v1 v1  
     1 == P2.8        Flexure tests ==
     2•       **Phase**               :       2 
     3•       **Status**              :       Draft   
     4•       **Category**            :       Daytime testing (functionality and operability) (C2)
     5•       **Recurrence**  :       once at commissioning
     6•       **Duration**            :       3 hour(s)
     7**Description**
     8•       This activity corresponds to the flexure tests for the SHARK-NIR.
     9**Prerequisites**
     10•       If relevant, estimate and remove the NCPA using phase-diversity method.
     11•       RR mounted on SX side.
     12**Procedure**
     13•       Test the positions of the various opto-mechanical components within the instrument using optical feedback while moving the telescope in elevation.
     14•       Change the velocity and acceleration of the movement of the telescope in elevation if required.
     15•       Remember to perform the tests for all the observing modes (whatever possible with RR or internal light sources)
     16•       You may want to disentangle the flexure of the RR while moving the telescope in elevation by comparing the optical feedback for the same movement with the internal light source.
     17•       This test will also test the working of the LBTO AO system while the telescope is moving in elevation.
     18•       Compare the results with that of Padova flexure tests.
     19**Success criteria**
     20•       All the images and data are saved for analysis or to create the lookup table.
     21**Notes**
     22•       If the test results are not satisfactory, this activity may be repeated again after making proper countermeasures to reduce the flexure.
     23**LBTO support**
     24•       Support from LBTI/LBTO?
     25**Associated SHARK-NIR personnel**
     26•       JF, LM, MdP
     27**Date performed and by whom**