wiki:docs/CommissioningPlan/P2.8

Version 1 (modified by kradhakrishnan, 5 years ago) (diff)

--

P2.8 Flexure tests

  • Phase : 2
  • Status : Draft
  • Category : Daytime testing (functionality and operability) (C2)
  • Recurrence : once at commissioning
  • Duration : 3 hour(s)

Description

  • This activity corresponds to the flexure tests for the SHARK-NIR.

Prerequisites

  • If relevant, estimate and remove the NCPA using phase-diversity method.
  • RR mounted on SX side.

Procedure

  • Test the positions of the various opto-mechanical components within the instrument using optical feedback while moving the telescope in elevation.
  • Change the velocity and acceleration of the movement of the telescope in elevation if required.
  • Remember to perform the tests for all the observing modes (whatever possible with RR or internal light sources)
  • You may want to disentangle the flexure of the RR while moving the telescope in elevation by comparing the optical feedback for the same movement with the internal light source.
  • This test will also test the working of the LBTO AO system while the telescope is moving in elevation.
  • Compare the results with that of Padova flexure tests.

Success criteria

  • All the images and data are saved for analysis or to create the lookup table.

Notes

  • If the test results are not satisfactory, this activity may be repeated again after making proper countermeasures to reduce the flexure.

LBTO support

  • Support from LBTI/LBTO?

Associated SHARK-NIR personnel

  • JF, LM, MdP

Date performed and by whom