wiki:docs/CommissioningPlan/P2.7

Version 9 (modified by kradhakrishnan, 4 years ago) (diff)

--

P2.7 Checking pointing offset between SHARK-NIR and SOUL-AO

  • Phase : 2
  • Status : Draft
  • Category : Daytime testing (functionality and operability) (C2)
  • Recurrence : once at commissioning
  • Duration : 3 days

Description

  • Test to check if there is a considerable pointing offset between the SHARK-NIR (SCICAM/TECCAM) and SOUL-AO as a function of the elevation of the telescope

Prerequisites

  • If relevant, estimate and remove the NCPA using the phase-diversity method.
  • RR mounted on SX side.

Procedure

  • Need to define the procedure?

Success criteria

  • Estimate the pointing offset and conclude if it is acceptable or not. If not acceptable, take proper actions to overcome this issue.

Notes

LBTO support

  • Authorize SHARK-NIR on the SX side.
  • RR mounted on the SX side.
  • Support from LBT SW Team, LBTI/Arcetri team to run SOUL AO

Associated SHARK-NIR personnel

Date performed and by whom

Comments

MB: Given the adjustment of SOULD LBT wrt to elevation should already have been done previsouly, I'd say it would be best to have also a look up table at least for TT where dichroic and in-TT are adjusted to compensate flexures [okay. in that case, we may need more time. lets discuss.]