    1  == P2.8        Looking for filter defects/effects/features ==
     1 == P2.7 Checking pointing offset between SHARK-NIR and SOUL-AO==
    22•       **Phase**               :       2 
    33•       **Status**              :       Draft   
    44•       **Category**            :       Daytime testing (functionality and operability) (C2)
    55•       **Recurrence**  :       once at commissioning
    6 •       **Duration**            :       2 days
     6•       **Duration**            :       3 days
    77**Description**
    8 •       Finding the filter defects/effects/features using different lamps within the instrument.
    9 •       If required, this may be repeated for on-axis source from RR for selected or all filters while the AO loop is running (daytime)
     8•       Test to check if there is a considerable pointing offset between the SHARK-NIR (SCICAM/TECCAM) and SOUL-AO as a function of the elevation of the telescope
    109**Prerequisites**
    1110•       If relevant, estimate and remove the NCPA using phase-diversity method.
    1211•       RR mounted on SX side.
    1312**Procedure**
    14 •       Take the images of all the filters using different lamps within the instrument to locate/find out the filter effects/defects/features.
    15 •       You may take short- and long-exposures to get better contrast of the features if required.
    16 •       This may be repeated with the on-axis source from the RR with AO running to check for any extra features arriving from outside SHARK-NIR but from LBT mirrors or the deployable arm.
    17 •       Repeat the science calibrations as done in [wiki:/docs/CommissioningPlan/P1.9 P1.9].
    18 * Perform the working of this monitoring activity [wiki:/docs/Commissioning/SNM1 Filter wheels reproducibility monitoring.]
     13•       Need to define the procedure?
    1914
    2015**Success criteria**
    21 •       All the filter images saved.
     16•       Estimate the pointing offset and conclude if it is acceptable or not. If not acceptable, take proper actions to overcome this issue.
    2217**Notes**
    23 •       The time dedicated to this activity has to be considered in combination with the next activity, if needed. Parallelism is possible.
     18
    2419**LBTO support**
    2520* Authorize SHARK-NIR on SX side.