    1 Cryostat Cooldown and Science detector calibrations ==
     1== P2.6 Tip-Tilt internal fast loop test with ASM turbulence ==
    22
    33- **Phase**             :       2 
    44- **Status**            :       Draft   
    5 - **Category**  :       Daytime testing (functionality and operability) (C3) + Daytime calibration (C4)
     5- **Category**  :       Daytime testing (functionality and operability) (C3)
    66- **Recurrence**        :       after instrument installation at telescope platform
    7 - **Duration**  :       1 day
     7- **Duration**  :       0.5 day
    88
    99**Description**
    10 - At the beginning of the next run, the cryostat is cooled down and the science detector calibrations are performed (when at the telescope).
     10- To verify the SHARK-NIR internal fast tip-tilt loop (using CRED1 and SHARK-NIR ALPAO DM) using the ARGOS light source (only at zenith) for various seeing conditions simulated at the ASM.
    1111
    1212**Prerequisites**
    13 
     13- Knowledge of Argos light source magnitude and the possibility to tune its brightness.
    1414
    1515**Procedure**
    16 - For the cryostat cool down, follow P1.4 and P1.5
    17 - For science detector calibrations follow P1.7
     16- Use ARGOS light source (to be used only at zenith) and direct light towards SHARK-NIR.
     17- Close the SOUL AO loop to have the best ASM shape. Keep the ASM static with the best shape.
     18- Close the SHARK-NIR internal tip-tilt loop.
     19- Take 10mins of data at the CRED2 and SCICAM.
     20- Introduce 0.5" seeing at the ASM and close the loop.
     21- Close the SHARK-NIR internal tip-tilt loop.
     22- Take 10mins of data at the CRED2 and SCICAM.
     23- Introduce 0.8" seeing at the ASM and close the loop.
     24- Close the SHARK-NIR internal tip-tilt loop.
     25- Take 10mins of data at the CRED2 and SCICAM.
     26- Repeat the above steps for the selected brightness of the Argos light source
    1827
    1928**Templates**
    2029
    2130**Success criteria**
    22 - Cryostat cooled down.
    23 - SHARK-NIR working normally.
    24 - Science calibrations are performed and new values are saved.
     31- SHARK-NIR fast tip-tilt loop working efficiently within the requirements in all the seeing conditions.
    2532
    2633**Notes**
    27 - Support from the Steward Observatory detector team.
     34- For the SN team: know in advance how many minutes of data can be downloaded from CRED2 or the ring-buffer size.
    2835
    2936**LBTO support**
    30 - Follow P1.4 and P1.5 (for the cryostat cool down)
     37- Authorize SHARK-NIR
     38- Permission to use SX-ASM and LBTI-AO
     39- AO support
    3140
    3241**Date performed and by whom**