wiki:docs/CommissioningPlan/P2.6

Version 23 (modified by kradhakrishnan, 2 years ago) (diff)

--

P2.6 Tip-Tilt internal fast loop test with ASM turbulence

  • Phase : 2
  • Status : Draft
  • Category : Daytime testing (functionality and operability) (C3)
  • Recurrence : after instrument installation at telescope platform
  • Duration : 0.5 day

Description

  • To verify the SHARK-NIR internal fast tip-tilt loop (using CRED1 and SHARK-NIR ALPAO DM) using the ARGOS light source (only at zenith) for various seeing conditions simulated at the ASM.

Prerequisites

  • Knowledge of Argos light source magnitude and the possibility to tune its brightness.

Procedure

  • Use ARGOS light source (to be used only at zenith) and direct light towards SHARK-NIR.
  • Close the SOUL AO loop to have the best ASM shape. Keep the ASM static with the best shape.
  • Close the SHARK-NIR internal tip-tilt loop.
  • Take 10mins of data at the CRED2 and SCICAM.
  • Introduce 0.5" seeing at the ASM and close the loop.
  • Close the SHARK-NIR internal tip-tilt loop.
  • Take 10mins of data at the CRED2 and SCICAM.
  • Introduce 0.8" seeing at the ASM and close the loop.
  • Close the SHARK-NIR internal tip-tilt loop.
  • Take 10mins of data at the CRED2 and SCICAM.
  • Repeat the above steps for the selected brightness of the Argos light source

Templates

Success criteria

  • SHARK-NIR fast tip-tilt loop working efficiently within the requirements in all the seeing conditions.

Notes

  • For the SN team: know in advance how many minutes of data can be downloaded from CRED2 or the ring-buffer size.

LBTO support

  • Authorize SHARK-NIR
  • Permission to use SX-ASM and LBTI-AO
  • AO support

Date performed and by whom