wiki:docs/CommissioningPlan/P2.5

Version 5 (modified by kradhakrishnan, 4 years ago) (diff)

--

P2.5 SOUL AO system tests

  • Phase : 2
  • Status : Draft
  • Category : Daytime testing (functionality and operability) (C2)
  • Recurrence : after instrument installation at telescope platform
  • Duration : 5 days

Description

  • Proper working of the SOUL AO system is essential for the performance of the SHARK-NIR instrument. Arcetri team optimizes the SOUL AO system grabbing the PSF image from the SHARK-NIR SCICAM. Argos swing arm calibration light source will be used. If this is not available, RR may be used (second choice only).

Prerequisites

  • SHARK-NIR active and working normally.
  • Cryostat cold and SCICAM working properly.
  • Activity P1.9 success criteria met.
  • Telescope pointed to Zenith and permission to use the Argos swing arm calibration unit.

Procedure

  • AO optimization procedure comes here

Success criteria

  • SOUL AO system working in tandem with the SAHRK-NIR system.
  • Acceptable improvement of the on-axis PSF (Argos Swing arm calibration light source) while SOUL AO is closed with known disturbances.
  • Get a new and improved daytime telescope model for SHARK-NIR, if necessary.

Notes

LBTO support

  • Authorize SHARK-NIR on the SX side.
  • Authorize mode to use the Argos Swing Arm. If not Argos swing arm, RR will be required on the SX side.
  • Support from LBT SW Team, LBTI/Arcetri team.

Associated SHARK-NIR personnel

Date performed and by whom