Changes between Version 17 and Version 18 of docs/CommissioningPlan/P2.5


Ignore:
Timestamp:
10/31/22 14:35:33 (2 years ago)
Author:
mbergomi
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan/P2.5

    v17 v18  
    1212**Prerequisites**
    1313- All electronics and services are up and running.
    14 - Cryostat is cooled down before the run (if not kept cooled between the runs). Check [wiki:/docs/CommissioningPlan/P1.4 P1.4] and [wiki:/docs/CommissioningPlan/P1.5 P1.5] for cryostat cool procedure.
    15 - Science detector calibrations are performed remotely before the run. Check [wiki:/docs/CommissioningPlan/P1.7 P1.7] for details.
     14- Some tests mentioned below may be performed remotely before the actual run (goal) or can occurr after handover, in case of availability of telescope due to bad weather.
    1615
    1716**Procedure**
    18 - Test all the TCS functionality (sending preset, ADC trajectory, etc.) needed by SHARK-NIR, detailed in AD2. Some tests mentioned below may happen in the previous run (on a best-effort basis) or have been performed remotely before the actual run.
     17- Test all the TCS functionality (sending preset, ADC trajectory, etc.) needed by SHARK-NIR, detailed in AD2.
    1918- Check if the fits-writer receives all the right values from the LBT TCS.
    20 - Check if the derotator trajectory is received from the LBT TCS. The trajectory verification with optical feedback will be done during the nighttime commissioning.
    21 - Re-check if SOUL can access the SCICAM image from the agreed-upon folder.
     19- Check if the derotator trajectory is received from the LBT TCS. The trajectory verification with optical feedback will be done during the nighttime commissioning (or at twilight if availability during the run will be granted).
     20- Re-check if SOUL can access the SCICAM image from the agreed-upon folder and test script with Alfio.
    2221
    2322**Templates**
     
    2625- Connection to LBT TCS is working well. All the test results are successful.
    2726- The fits-writer is receiving all the right values from LBT TCS.
    28 - SOUL can retieve the SCICAM image.
     27- SOUL can retrieve the SCICAM image.
    2928
    3029**Notes**
     
    3534- Permission to use SX-ASM and LBTI-AO
    3635- Permission to send preset, receiving LBT telemetry (inc. the derotator trajectory) and details for the Fitswriter.
    37 - Support from the LBT SW team for the TCS communication tests.
     36- Support from the LBT SW team and John Hill for the TCS communication tests.
    3837
    3938**Date performed and by whom**
     39D. Ricci is contact point for this task. Tests will be spread in several days, ahead of Pre-com-3 and during Pre-com-3. SOUL test will be performed between Nov. 15th and 24th.