wiki:docs/CommissioningPlan/P2.5

Version 17 (modified by kradhakrishnan, 2 years ago) (diff)

--

P2.5 TCS communication test

  • Phase : 2
  • Status : Draft
  • Category : Daytime testing (functionality and operability) (C3)
  • Recurrence : after instrument installation at telescope platform
  • Duration : 1 day

Description

  • Check the communication between the LBT TCS and SHARK-NIR system.

Prerequisites

  • All electronics and services are up and running.
  • Cryostat is cooled down before the run (if not kept cooled between the runs). Check P1.4 and P1.5 for cryostat cool procedure.
  • Science detector calibrations are performed remotely before the run. Check P1.7 for details.

Procedure

  • Test all the TCS functionality (sending preset, ADC trajectory, etc.) needed by SHARK-NIR, detailed in AD2. Some tests mentioned below may happen in the previous run (on a best-effort basis) or have been performed remotely before the actual run.
  • Check if the fits-writer receives all the right values from the LBT TCS.
  • Check if the derotator trajectory is received from the LBT TCS. The trajectory verification with optical feedback will be done during the nighttime commissioning.
  • Re-check if SOUL can access the SCICAM image from the agreed-upon folder.

Templates

Success criteria

  • Connection to LBT TCS is working well. All the test results are successful.
  • The fits-writer is receiving all the right values from LBT TCS.
  • SOUL can retieve the SCICAM image.

Notes

  • Alfio Puglisi is the contact point for the SOUL access to SCICAM images.

LBTO support

  • Authorize SHARK-NIR
  • Permission to use SX-ASM and LBTI-AO
  • Permission to send preset, receiving LBT telemetry (inc. the derotator trajectory) and details for the Fitswriter.
  • Support from the LBT SW team for the TCS communication tests.

Date performed and by whom