    1 == P2.5 Instrument functional checks including TCS communication test ==
     1== P2.5 TCS communication test ==
    22
    33- **Phase**             :       2 
     
    88
    99**Description**
    10 - Instrumental functional checks are performed, including the communication between the LBT TCS and SHARK-NIR system.
     10- Check the communication between the LBT TCS and SHARK-NIR system.
    1111
    1212**Prerequisites**
     
    1616
    1717**Procedure**
    18 - Basic SHARK-NIR functional tests are performed. Images are taken using the SCICAM using SHARK-NIR internal calibration sources.
    1918- Test all the TCS functionality (sending preset, ADC trajectory, etc.) needed by SHARK-NIR, detailed in AD2. Some tests mentioned below may happen in the previous run (on a best-effort basis) or have been performed remotely before the actual run.
    2019- Check if the fits-writer receives all the right values from the LBT TCS.
     
    2524
    2625**Success criteria**
    27 - All the functional checks are successfully completed.
    2826- Connection to LBT TCS is working well. All the test results are successful.
    2927- The fits-writer is receiving all the right values from LBT TCS.