Changes between Version 15 and Version 16 of docs/CommissioningPlan/P2.5
- Timestamp:
- 09/21/22 11:49:02 (2 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan/P2.5
v15 v16 12 12 **Prerequisites** 13 13 - All electronics and services are up and running. 14 - Cryostat is cooled down before the run (if not kept cooled between the runs). 15 - Science detector calibrations are performed remotely before the run. 14 - Cryostat is cooled down before the run (if not kept cooled between the runs). Check [wiki:/docs/CommissioningPlan/P1.4 P1.4] and [wiki:/docs/CommissioningPlan/P1.5 P1.5] for cryostat cool procedure. 15 - Science detector calibrations are performed remotely before the run. Check [wiki:/docs/CommissioningPlan/P1.7 P1.7] for details. 16 16 17 17 **Procedure**