P2.5 Instrument functional checks including TCS communication test
- Phase : 2
- Status : Draft
- Category : Daytime testing (functionality and operability) (C3)
- Recurrence : after instrument installation at telescope platform
- Duration : 1 day
Description
- Instrumental functional checks are performed, including the communication between the LBT TCS and SHARK-NIR system.
Prerequisites
- All electronics and services are up and running.
- Cryostat is cooled down before the run (if not kept cooled between the runs).
- Science detector calibrations are performed remotely before the run.
Procedure
- Basic SHARK-NIR functional tests are performed. Images are taken using the SCICAM using SHARK-NIR internal calibration sources.
- Test all the TCS functionality (sending preset, ADC trajectory, etc.) needed by SHARK-NIR, detailed in AD2. Some tests mentioned below may happen in the previous run (on a best-effort basis) or have been performed remotely before the actual run.
- Check if the fits-writer receives all the right values from the LBT TCS.
- Check if the derotator trajectory is received from the LBT TCS. The trajectory verification with optical feedback will be done during the nighttime commissioning.
- Re-check if SOUL can access the SCICAM image from the agreed-upon folder.
Templates
Success criteria
- All the functional checks are successfully completed.
- Connection to LBT TCS is working well. All the test results are successful.
- The fits-writer is receiving all the right values from LBT TCS.
- SOUL can retieve the SCICAM image.
Notes
- Alfio Puglisi is the contact point for the SOUL access to SCICAM images.
LBTO support
- Authorize SHARK-NIR
- Permission to use SX-ASM and LBTI-AO
- Permission to send preset, receiving LBT telemetry (inc. the derotator trajectory) and details for the Fitswriter.
- Support from the LBT SW team for the TCS communication tests.
Date performed and by whom