    1 == P2.5 TCS communication test ==
     1== P2.5 Instrument functional checks including TCS communication test ==
    22
    33- **Phase**             :       2 
     
    88
    99**Description**
    10 - Communication with the LBT TCS is tested to verify that the interface with TCS works as expected.
     10- Instrumental functional checks are performed, including the communication between the LBT TCS and SHARK-NIR system.
    1111
    1212**Prerequisites**
    1313- All electronics and services are up and running.
     14- Cryostat is cooled down before the run (if not kept cooled between the runs).
     15- Science detector calibrations are performed remotely before the run.
    1416
    1517**Procedure**
    16 - Test all the TCS functionality (sending preset, ADC trajectory, etc.) needed by SHARK-NIR, detailed in AD2.
    17 - Check if the fits-writer is receiving all the right values from the LBT TCS.
     18- Basic SHARK-NIR functional tests are performed. Images are taken using the SCICAM using SHARK-NIR internal calibration sources.
     19- Test all the TCS functionality (sending preset, ADC trajectory, etc.) needed by SHARK-NIR, detailed in AD2. Some tests mentioned below may happen in the previous run (on a best-effort basis) or have been performed remotely before the actual run.
     20- Check if the fits-writer receives all the right values from the LBT TCS.
    1821- Check if the derotator trajectory is received from the LBT TCS. The trajectory verification with optical feedback will be done during the nighttime commissioning.
    1922- Re-check if SOUL can access the SCICAM image from the agreed-upon folder.
     
    2225
    2326**Success criteria**
     27- All the functional checks are successfully completed.
    2428- Connection to LBT TCS is working well. All the test results are successful.
    2529- The fits-writer is receiving all the right values from LBT TCS.
     
    2731
    2832**Notes**
    29 - Arcetri Team remote support is required.
    30 - LBTI-AO team support is required.
    31 - Note that although the actual work needs roughly about 2 days, a lot of it can go in parallel with other activites. So, for the estimation of the total days, only 1 day from here is considered.
     33- Alfio Puglisi is the contact point for the SOUL access to SCICAM images.
    3234
    3335**LBTO support**
     
    3537- Permission to use SX-ASM and LBTI-AO
    3638- Permission to send preset, receiving LBT telemetry (inc. the derotator trajectory) and details for the Fitswriter.
    37 - Support from the LBT SW team
     39- Support from the LBT SW team for the TCS communication tests.
    3840
    3941**Date performed and by whom**