P2.3 TCS communication test

  • Phase : 2
  • Status : Draft
  • Category : Daytime testing (functionality and operability) (C2)
  • Recurrence : after instrument installation at telescope platform
  • Duration : 1 hour(s)

Description

  • Communication with the LBT TCS is tested, with the aim to verify that the interface with TCS works as expected.

Prerequisites

  • All electronics and services up and running.

Procedure

  • Test all the TCS functionality needed by SHARK-NIR, which are detailed in AD2.
  • Check if the fits-writer is receiving all the right values from the LBT TCS.
  • Check if the derotator trajectory is received from the LBT TCS. The final testing of the trajectory with optical feedback will be done during the night time commissioning.

Success criteria

  • Connection to LBT TCS working well. All the test results are successful.
  • Fits-writer is receiving all the right values from LBT TCS.

Notes LBTO support Associated SHARK-NIR personnel

  • JF, LM, MdP, MM (from AZ), Dino?

Date performed and by whom