Changes between Version 16 and Version 17 of docs/CommissioningPlan/P2.3
- Timestamp:
- 09/07/22 20:14:05 (2 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan/P2.3
v16 v17 20 20 - Check the shutdown procedure. 21 21 - Testing the electronics and SW rotation of the knob controlling the cool down process (LBTI side). 22 - Cool down the cryostat. 22 23 23 24 24 **Procedure for Basic Functionality** … … 36 36 - All systems are turned on, and the services are all running without any errors. 37 37 - The shutdown procedure is checked and working as it should be. 38 - Cryostat cooling started and is on track.39 38 - Motors and light sources are working as they should. 40 39 - The internal alignment is preserved.