    1 == P2.3 TCS communication test ==
     1== P2.3 Basic functionality, Instrument Operability and Functioning ==
    22
    33- **Phase**             :       2 
    44- **Status**            :       Draft   
    5 - **Category**  :       Daytime testing (functionality and operability)  (C3)   
    6 - **Recurrence**        :       after instrument installation at telescope platform
    7 - **Duration**  :       2 days
     5- **Category**  :       Daytime testing (functionality and operability) (C3)                           
     6- **Recurrence**        :       once after instrument installation at telescope platform
     7- **Duration**  :       1 day
    88
    99**Description**
    10 - Communication with the LBT TCS is tested to verify that the interface with TCS works as expected.
     10- Activating the instrument after the installation of SHARK-NIR at the telescope platform. Verification of the shutdown procedure.
    1111
    1212**Prerequisites**
    13 - All electronics and services are up and running.
     13- SHARK-NIR is installed on the LBT telescope platform.
    1414
    1515**Procedure**
    16 - Test all the TCS functionality (sending preset, ADC trajectory, etc.) needed by SHARK-NIR, detailed in AD2.
    17 - Check if the fits-writer is receiving all the right values from the LBT TCS.
    18 - Check if the derotator trajectory is received from the LBT TCS. The trajectory verification with optical feedback will be done during the nighttime commissioning.
    19 - Re-check if SOUL can access the SCICAM image from the agreed-upon folder.
     16- Switch on all the cabinets, follow the instrument telemetry and see if the telemetry is logging.
     17- Turn all the hardware subsystems turned on and start all the corresponding services. Check all the logs from the services.
     18- Check the shutdown procedure.
     19- Testing the electronics and SW rotation of the knob controlling the cool down process (LBTI side).
     20- Cool down the cryostat.
    2021
    21 **Templates** 
     22**Templates**
    2223
    2324**Success criteria**
    24 - Connection to LBT TCS is working well. All the test results are successful.
    25 - The fits-writer is receiving all the right values from LBT TCS.
    26 - SOUL can retieve the SCICAM image.
     25- Activating instrument successfully.
     26- All systems are turned on, and the services are all running without any errors.
     27- The shutdown procedure is checked and working as it should be.
     28- Cryostat cooling started and is on track.
    2729
    2830**Notes**
    29 - Arcetri Team remote support is required.
    30 - LBTI-AO team support is required.
    31 - Note that although the actual work needs roughly about 2 days, a lot of it can go in parallel with other activites. So, for the estimation of the total days, only 1 day from here is considered.
    3231
    3332**LBTO support**
    34 - Authorize SHARK-NIR
    35 - Permission to use SX-ASM and LBTI-AO
    36 - Permission to send preset, receiving LBT telemetry (inc. the derotator trajectory) and details for the Fitswriter.
    37 - Support from the LBT SW team
     33- Testing the working of the knob (motor or manual) controlling the cooldown.
     34- Liquid Nitrogen fill.
     35- Vacuum pump (See activity P1.4 and P1.5 for more details).
    3836
    3937**Date performed and by whom**