    1010•       All electronics and services up and running.
    1111**Procedure**
    12 •       Test all the TCS functionality needed by SHARK-NIR, which are detailed in AD2.
     12•       Test all the TCS functionality (sending preset, ADC trajectory, etc.) needed by SHARK-NIR, which are detailed in AD2.
    1313•       Check if the fits-writer is receiving all the right values from the LBT TCS.
    1414•       Check if the derotator trajectory is received from the LBT TCS. The final testing of the trajectory with optical feedback will be done during the night time commissioning.
    15 
     15* Re-check if SOUL can access the SCICAM image from the agreed-upon folder.
    1616**Success criteria**
    1717•       Connection to LBT TCS working well. All the test results are successful.
    1818•       Fits-writer is receiving all the right values from LBT TCS.
     19* SOUL can retieve the SCICAM image.
    1920**Notes**
    2021
     
    2728
    2829**Associated SHARK-NIR personnel**
    29 
     30* Arcetri Team
    3031
    3132**Date performed and by whom**
    3233
    3334**Comments**
    34 
    35 MB: perhaps let's add here the check that SOUL can retrieve images from SCICAM [This needs support from Arcetri team.]
    36 
    37 MB: also ADC trajectories might be tested here. Let's ask luca/Vale/depa [ok]
    38 
    39 MB: add also sending presets to the telescope [i thought it is there in AD2]