P2.2 Installation of SHARK-NIR and its electronics on the LBT platform

  • Phase : 2
  • Status : Draft
  • Category : Installation of SHARK-NIR at LBT platform (C2)
  • Recurrence : once (unless deemed necessary to remove SHARK-NIR from the telescope platform)
  • Duration : 7 days (including 1 day contingency)

Description

  • Aligned SHARK-NIR is prepared for the Big-Lift and installed on the LBT platform.
  • Installation of the electronics in the cabinets, cabling, and confirming the safety & security of the instrument and area.

Prerequisites

  • SHARK-NIR is aligned and ready for the lift-off.
  • People required to access the electronics platform have completed the needed training

Procedure

  • Look at the AD3 document for the procedure and details.

Templates

Success criteria

  • SHARK-NIR is successfully installed on the LBT platform.
  • SHARK-NIR electronics are successfully installed.
  • Telescope is balanced.
  • Connect all the cables and secure them.
  • Reassure all the connections, nuts, bolts, etc.
  • Confirm the safety and security of the instrument and the area.

Notes

  • Activities on High-bay and telescope.
  • Note that SHARK-NIR is NOT installed as a single piece. The cryostat has to be disassembled from the bearing before the installation can start. Please look into the AD3 document for details.
  • Note that one (or two) rack(s) of the SHARK-NIR electronics are installed within the LBTI electronics cabinets (shared with LBTI and iLocater).
  • Input from Laura Funk (LBTO): Installation of the LBT work platform takes around 2 hours and of course also its removal. If the telescope installation is performed during the observing semester, carefully plan activities that can be completed so as not to interfere with handover for nighttime observations (~2 hours before sunset).
  • check this link (https://docs.google.com/document/d/1r0SDiy9yBEfGQjDI6hCXT9hfRDRJ4dh4nNUZ3JHClJE/edit) for some details on the alignment day to day plan.

LBTO support

  • Crew members' support for the preparation, lift-off, and installation of SHARK-NIR and its electronics
  • Crane operator (cleanroom, mountain bay, LBT platform)
  • Safety officer
  • Working platform installed in front of the Gregorian focal-station SX
  • Hatch door SX on the UIAP platform removed
  • Support for the installation of electronics in the LBTO cabinet
  • Kindly check the installation document, AD3, for more details