P2.2 Instrument operability and performance
- Phase : 2
- Status : Draft
- Category : Daytime testing (functionality and operability)
- Recurrence : after instrument installation at telescope platform
- Duration : 3 hour(s)
Description
- The functionality and operability of individual components/subsystems are tested. This is followed by the checking of the internal alignment of the instrument using the light source within. The final step is the performances of the system.
Prerequisites
- All electronics and services up and running.
Procedure
- Initialize all the motors/sub-systems.
- Check the functionality of all the motors (home position, named/nominal positions, and reaching software limits).
- Check the working of all the light sources.
- Using the on-axis diffraction-limited light source, check the internal alignment of the SHARK-NIR.
- Finally, the performance of the system is again verified after the installation.
Success criteria
- Motors and light sources working as they should.
- The internal alignment is preserved.
- Performance of the system is acceptable.
Notes LBTO support Associated SHARK-NIR personnel
- JF, LM, MdP, MM (from AZ)
Date performed and by whom