Changes between Version 4 and Version 5 of docs/CommissioningPlan/P2.2


Ignore:
Timestamp:
01/19/21 11:13:29 (4 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan/P2.2

    v4 v5  
    44•       **Category**            :       Daytime testing (functionality and operability) (C2)                           
    55•       **Recurrence**  :       after instrument installation at telescope platform
    6 •       **Duration**            :       1 dyay
     6•       **Duration**            :       1 day
    77**Description**
    88•       The functionality and operability of individual components/subsystems are tested. This is followed by the checking of the internal alignment of the instrument using the light source within. The final step is the performances of the system.