    1 == P2.2 Installation of SHARK-NIR and its electronics on the LBT platform==
     1== [[span(style=color: green, **P2.2 Installation of SHARK-NIR and its electronics on the LBT platform** )]] ==
    22
    33- **Phase**             :       2 
    4 - **Status**            :       Draft   
     4- **Status**            :       [[span(style=color: green, **COMPLETE** )]]     
    55- **Category**  :       Installation of SHARK-NIR at LBT platform (C2) 
    66- **Recurrence**        :       once (unless deemed necessary to remove SHARK-NIR from the telescope platform)
     
    6565- Note that othe Lakeshore of the SHARK-NIR electronics is installed within the LBTI electronics cabinets, the rest of the electronics is in the cabinet shared with  iLocater.
    6666- check this link (https://docs.google.com/document/d/1r0SDiy9yBEfGQjDI6hCXT9hfRDRJ4dh4nNUZ3JHClJE/edit) for some details on the alignment day to day plan.
    67 
     67- Considering October timelines, as per LBTO information. Platform installation can start at 08:00 and takes about 40 minutes. 2 people can handle it. Platform use stops at 16:00, and dismounting takes about 30 mins.
     68- No extra crew is needed on the telescope during weekends for the platform, as the operation can be handled by personnel already available at the telescope.
    6869
    6970**LBTO support**
     
    8182
    8283**Notes**
    83 Considering October timelines, as per LBTO information. Platform installation can start at 08:00 and takes about 40 minutes. 2 people can handle it. Platform use stops at 16:00, and dismounting takes about 30 mins.
    84 No extra crew is needed on the telescope during weekends for the platform, as the operation can be handled by personnel already available at the telescope.