Changes between Version 32 and Version 33 of docs/CommissioningPlan/P2.2
- Timestamp:
- 10/28/22 18:25:43 (2 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan/P2.2
v32 v33 1 == P2.2 Installation of SHARK-NIR and its electronics on the LBT platform==1 == [[span(style=color: green, **P2.2 Installation of SHARK-NIR and its electronics on the LBT platform** )]] == 2 2 3 3 - **Phase** : 2 4 - **Status** : Draft4 - **Status** : [[span(style=color: green, **COMPLETE** )]] 5 5 - **Category** : Installation of SHARK-NIR at LBT platform (C2) 6 6 - **Recurrence** : once (unless deemed necessary to remove SHARK-NIR from the telescope platform) … … 65 65 - Note that othe Lakeshore of the SHARK-NIR electronics is installed within the LBTI electronics cabinets, the rest of the electronics is in the cabinet shared with iLocater. 66 66 - check this link (https://docs.google.com/document/d/1r0SDiy9yBEfGQjDI6hCXT9hfRDRJ4dh4nNUZ3JHClJE/edit) for some details on the alignment day to day plan. 67 67 - Considering October timelines, as per LBTO information. Platform installation can start at 08:00 and takes about 40 minutes. 2 people can handle it. Platform use stops at 16:00, and dismounting takes about 30 mins. 68 - No extra crew is needed on the telescope during weekends for the platform, as the operation can be handled by personnel already available at the telescope. 68 69 69 70 **LBTO support** … … 81 82 82 83 **Notes** 83 Considering October timelines, as per LBTO information. Platform installation can start at 08:00 and takes about 40 minutes. 2 people can handle it. Platform use stops at 16:00, and dismounting takes about 30 mins.84 No extra crew is needed on the telescope during weekends for the platform, as the operation can be handled by personnel already available at the telescope.