Changes between Version 29 and Version 30 of docs/CommissioningPlan/P2.2


Ignore:
Timestamp:
09/08/22 19:12:31 (2 years ago)
Author:
lmarafatto
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan/P2.2

    v29 v30  
    2424    - camera on a cart with wheels (with a window on the bottom): lift up through the hatch or use elevators
    2525  - **Day 1**
    26     - Shelves installation.
     26    - Shelves installation. (Pag. 70-89 of Installation Plan: SHARK-NIR-INAFP-MAN-001_Issue2.1)
    2727  - **Day 2**
    28     - 2 Rails installation.
    29     - Installation of calendered structure on the shelves. At the end of the day calendered structure shall be secured to the shelves, otherwise it shall be removed, together with installation rails and procedure repeataed the next day.
     28    - 2 Rails installation. (Pag. 90-95 of Installation Plan: SHARK-NIR-INAFP-MAN-001_Issue2.1)
     29    - Installation of calendered structure on the shelves. (Pag. 95-111). At the end of the day calendered structure shall be secured to the shelves, otherwise it shall be removed, together with installation rails and procedure repeataed the next day.
    3030  - **Day 3**
    31     - Install the SHARK-NIR optic bench on the calendered structure.
     31    - Install the SHARK-NIR optic bench on the calendered structure. (Pag. 111-141)
    3232  - **Day 4**
    33     - Fix the cable chain.
    34     - Install patch boxes.
     33    - Fix the cable chain. (Pag. 142-144)
     34    - Install patch boxes. (Pag. 144-145)
    3535    - Fix cable from patch-boxes to instrument.
    3636  - **Day 5**
    37     - Move the calendered structure at its final position.
    38     - SCICAM installation with MACIE already installed.
     37    - Move the calendered structure at its final position. (Pag. 145-148)
     38    - SCICAM installation with MACIE already installed. (Pag. 148-163)
    3939    - Installation of electronics and cabling from patch boxes to cabinets.
    40     - Prepare the deployable arm for its handling.
     40    - Prepare the deployable arm for its handling. (Pag. 164-171)
    4141  - **Day 6**
    42     - Installation of the deployable arm.
     42    - Installation of the deployable arm. (Pag. 172-177)
    4343    - Complete cabling.
    4444    - Check movements of bearing, deployable arm, and shutter.