Changes between Version 25 and Version 26 of docs/CommissioningPlan/P2.2
- Timestamp:
- 09/07/22 20:05:14 (2 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan/P2.2
v25 v26 27 27 - **Day 2** 28 28 - 2 Rails installation. 29 - Installation of calendered structure on the rails.29 - Installation of calendered structure on the shelves. At the end of the day calendered structure shall be secured to the shelves, otherwise it shall be removed, together with installation rails and procedure repeataed the next day. 30 30 - **Day 3** 31 31 - Install the SHARK-NIR optic bench on the calendered structure.