25 | | - Shelves installation. |
26 | | - 2 Rails installation. |
27 | | - Installation of calendered structure on the rails. |
28 | | - Install the SHARK-NIR optic bench on the calendered structure. |
29 | | - Fix the cable chain. |
30 | | - Install patch boxes. |
31 | | - Fix cable from patch-boxes to instrument. |
32 | | - Installation of calendered structure at its final level. |
33 | | - SCICAM installation with MACIE already installed. |
34 | | - Installation of electronics and cabling from patchboxes to cabinets. |
35 | | - Installation of the deployable arm onto its handling. |
36 | | - Complete cabling. |
37 | | - Check movements of bearing, deployable arm, and shutter. |
38 | | - Cool down Cryostat. |
39 | | - Check the network connections and very basic functionalities after powering on. |
40 | | |
41 | | |
| 25 | - **Day 1** |
| 26 | - Shelves installation. |
| 27 | - **Day 2** |
| 28 | - 2 Rails installation. |
| 29 | - Installation of calendered structure on the rails. |
| 30 | - **Day 3** |
| 31 | - Install the SHARK-NIR optic bench on the calendered structure. |
| 32 | - **Day 4** |
| 33 | - Fix the cable chain. |
| 34 | - Install patch boxes. |
| 35 | - Fix cable from patch-boxes to instrument. |
| 36 | - **Day 5** |
| 37 | - Installation of calendered structure at its final level. |
| 38 | - SCICAM installation with MACIE already installed. |
| 39 | - Installation of electronics and cabling from patch boxes to cabinets. |
| 40 | - Prepare the deployable arm for its handling. |
| 41 | - **Day 6** |
| 42 | - Installation of the deployable arm. |
| 43 | - Complete cabling. |
| 44 | - Check movements of bearing, deployable arm, and shutter. |
| 45 | - Cool down Cryostat. |
| 46 | - Check the network connections and very basic functionalities after powering on. |
| 47 | - **Day 7** |
| 48 | - Contingency |
| 49 | |