Changes between Version 23 and Version 24 of docs/CommissioningPlan/P2.2


Ignore:
Timestamp:
09/07/22 14:13:05 (2 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan/P2.2

    v23 v24  
    1616
    1717**Procedure**
    18 - Look at the AD3 document for the procedure and details.
     18- Look at the AD3 document for the detailed procedure.
     19  -  SHARK-NIR and its parts will be ready on the high bay. These components may be moved through the hatch to the telescope or moved by elevator to the telescope
     20    - shelves: use elevators
     21    - rails: use elevators
     22    - calendered structure: use elevators
     23    - shark-nir bench+ bearing on its red handling: lift up through the hatch.
     24    - camera on a cart with wheels (with a window on the bottom): lift up through the hatch or use elevators
     25  -  Shelves installation.
     26  - 2 Rails installation.
     27  - Installation of calendered structure on the rails.
     28  - Install the SHARK-NIR optic bench on the calendered structure.
     29  - Fix the cable chain.
     30  - Install patch boxes.
     31  - Fix cable from patch-boxes to instrument.
     32  - Installation of calendered structure at its final level.
     33  - SCICAM installation with MACIE already installed.
     34  - Installation of electronics and cabling from patchboxes to cabinets.
     35  - Installation of the deployable arm onto its handling.
     36  - Complete cabling.
     37  - Check movements of bearing, deployable arm, and shutter.
     38  - Cool down Cryostat.
     39  - Check the network connections and very basic functionalities after powering on.
     40
    1941
    2042**Templates**
     
    3254- Note that SHARK-NIR is NOT installed as a single piece. The cryostat has to be disassembled from the bearing before the installation can start. Please look into the AD3 document for details.
    3355- Note that one (or two) rack(s) of the SHARK-NIR electronics are installed within the LBTI electronics cabinets (shared with LBTI and iLocater).
    34 - Input from Laura Funk (LBTO): Installation of the LBT work platform takes around 2 hours and of course also its removal. If the telescope installation is performed during the observing semester, carefully plan activities that can be completed so as not to interfere with handover for nighttime observations (~2 hours before sunset).
     56- Input from Laura Funk (LBTO): Installation of the LBT work platform takes around 2 hours and, of course, also its removal. If the telescope installation is performed during the observing semester, carefully plan activities that can be completed so as not to interfere with handover for nighttime observations (~2 hours before sunset).
    3557- check this link (https://docs.google.com/document/d/1r0SDiy9yBEfGQjDI6hCXT9hfRDRJ4dh4nNUZ3JHClJE/edit) for some details on the alignment day to day plan.
    3658
     
    4870
    4971**Notes**
    50 Considering October timelines, as per LBTO information. Platform installation can start at 08:00 and takes about 40 minutes. It can be handled by 2 people. PLatform use stops at 16:00 and dismounting takes about 30 mins.
    51 No extra crew is needed on the telescope during weekends for platform, as the operation can be handled by person already available at the telescope.
     72Considering October timelines, as per LBTO information. Platform installation can start at 08:00 and takes about 40 minutes. 2 people can handle it. Platform use stops at 16:00, and dismounting takes about 30 mins.
     73No extra crew is needed on the telescope during weekends for the platform, as the operation can be handled by personnel already available at the telescope.