    v12 v13  
    44•       **Category**            :       Daytime testing (functionality and operability) (C2)                           
    55•       **Recurrence**  :       after instrument installation at telescope platform
    6 •       **Duration**            :       1 day
     6•       **Duration**            :       2 day
    77**Description**
    88•       The functionality and operability of individual components/subsystems are tested. This is followed by the checking of the internal alignment of the instrument using the light source within. The final step is the performance of the system.