    66•       **Duration**            :       1 day
    77**Description**
    8 •       Activating the instrument after the installation of SHARK-NIR at the telescope platform. Also, various instrument states will be tested including the emergency shutdown switch.
     8•       Activating the instrument after the installation of SHARK-NIR at the telescope platform. Also, the shutdown procedure will be checked.
    99**Prerequisites**
    1010•       SHARK-NIR installed on the LBT telescope platform.
     
    1212•       Switch on all the cabinets, follow the instrument telemetry and see if the telemetry is logging.
    1313•       Turn on all the hardware subsystems turned on and start all the corresponding services. Check all the logs from the services.
    14 •       Start the cryostat is cool down.
    15 •       Test the emergency shutdown button.
    16 •       Testing the electronics and SW rotation of the knob controlling the cool down process (LBTO side. Maria knows more details)
     14•       Check the shutdown procedure (except the cryostat warm-up).
     15•       Testing the electronics and SW rotation of the knob controlling the cool down process (LBTI side.)
    1716•       Cool down the cryostat
    1817**Success criteria**
    1918•       Activating instrument successfully.
    2019•       All systems turned on and the services all running without any errors.
     20* The shutdown procedure is checked and working as it should be.
    2121•       Cryostat cooling started and on-track.
    22 •       Emergency shutdown button working correctly.
     22
    2323**Notes**
    2424
    2525**LBTO support**
    26 •       Communicate while checking the emergency shutdown button.
    2726•       Testing the electronics and SW working of the knob (motor) controlling the cooldown.
    2827* Liquid Nitrogen fill
     
    3534MB: cabling between cabinet and SHARK-NIR patch boxes for motors and panel for other needs to take place either on the instalaltion, here or adding a point in between.
    3635
    37 MB: No button is foreseen. However shutdown procedure should be checked
    38 
    39 MB: Knob controlling is LBTI side not LBTO