Changes between Version 7 and Version 8 of docs/CommissioningPlan/P2.1
- Timestamp:
- 01/26/21 16:36:58 (4 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan/P2.1
v7 v8 6 6 • **Duration** : 1 day 7 7 **Description** 8 • Activating the instrument after the installation of SHARK-NIR at the telescope platform. Also, various instrument states will be tested including the emergency shutdown switch.8 • Activating the instrument after the installation of SHARK-NIR at the telescope platform. Also, the shutdown procedure will be checked. 9 9 **Prerequisites** 10 10 • SHARK-NIR installed on the LBT telescope platform. … … 12 12 • Switch on all the cabinets, follow the instrument telemetry and see if the telemetry is logging. 13 13 • Turn on all the hardware subsystems turned on and start all the corresponding services. Check all the logs from the services. 14 • Start the cryostat is cool down. 15 • Test the emergency shutdown button. 16 • Testing the electronics and SW rotation of the knob controlling the cool down process (LBTO side. Maria knows more details) 14 • Check the shutdown procedure (except the cryostat warm-up). 15 • Testing the electronics and SW rotation of the knob controlling the cool down process (LBTI side.) 17 16 • Cool down the cryostat 18 17 **Success criteria** 19 18 • Activating instrument successfully. 20 19 • All systems turned on and the services all running without any errors. 20 * The shutdown procedure is checked and working as it should be. 21 21 • Cryostat cooling started and on-track. 22 • Emergency shutdown button working correctly. 22 23 23 **Notes** 24 24 25 25 **LBTO support** 26 • Communicate while checking the emergency shutdown button.27 26 • Testing the electronics and SW working of the knob (motor) controlling the cooldown. 28 27 * Liquid Nitrogen fill … … 35 34 MB: cabling between cabinet and SHARK-NIR patch boxes for motors and panel for other needs to take place either on the instalaltion, here or adding a point in between. 36 35 37 MB: No button is foreseen. However shutdown procedure should be checked38 39 MB: Knob controlling is LBTI side not LBTO