Changes between Version 13 and Version 14 of docs/CommissioningPlan/P2.1
- Timestamp:
- 01/14/22 14:53:53 (3 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan/P2.1
v13 v14 1 == P2.1 Activating the instrument, basic check, initiate cryostat cool down == 2 • **Phase** : 2 3 • **Status** : Draft 4 • **Category** : Daytime testing (functionality and operability) (C3) 5 • **Recurrence** : after instrument installation at telescope platform 6 • **Duration** : 1 day 1 == P2.1 Basic functionality and shutdown procedure test, cryostat cooldown == 2 3 - **Phase** : 2 4 - **Status** : Draft 5 - **Category** : Daytime testing (functionality and operability) (C3) 6 - **Recurrence** : once after instrument installation at telescope platform 7 - **Duration** : 1 day 8 7 9 **Description** 8 • Activating the instrument after the installation of SHARK-NIR at the telescope platform. Also, the shutdown procedure will be checked. 10 - Activating the instrument after the installation of SHARK-NIR at the telescope platform. Verification of the shutdown procedure. 11 9 12 **Prerequisites** 10 • SHARK-NIR installed on the LBT telescope platform. 13 - SHARK-NIR is installed on the LBT telescope platform. 14 11 15 **Procedure** 12 • Switch on all the cabinets, follow the instrument telemetry and see if the telemetry is logging. 13 • Turn on all the hardware subsystems turned on and start all the corresponding services. Check all the logs from the services. 14 • Check the shutdown procedure (except the cryostat warm-up). 15 • Testing the electronics and SW rotation of the knob controlling the cool down process (LBTI side.) 16 • Cool down the cryostat 16 - Switch on all the cabinets, follow the instrument telemetry and see if the telemetry is logging. 17 - Turn all the hardware subsystems turned on and start all the corresponding services. Check all the logs from the services. 18 - Check the shutdown procedure (except the cryostat warm-up). 19 - Testing the electronics and SW rotation of the knob controlling the cool down process (LBTI side). 20 - Cooldown the cryostat. 21 22 **Templates** 23 17 24 **Success criteria** 18 •Activating instrument successfully.19 • All systems turned on and the servicesall running without any errors.20 *The shutdown procedure is checked and working as it should be.21 • Cryostat cooling started and on-track.25 - Activating instrument successfully. 26 - All systems are turned on, and the services are all running without any errors. 27 - The shutdown procedure is checked and working as it should be. 28 - Cryostat cooling started and is on track. 22 29 23 30 **Notes** 24 31 25 32 **LBTO support** 26 • Testing the working of the knob (motor/manual) controlling the cooldown. 27 * Liquid Nitrogen fill 28 * Vacuum pump 29 **Associated SHARK-NIR personnel** 33 - Testing the working of the knob (motor or manual) controlling the cooldown. 34 - Liquid Nitrogen fill 35 - Vacuum pump 30 36 31 37 **Date performed and by whom** 32 33 **Comments**34 35