    1 == P2.1 Activating the instrument, basic check, initiate cryostat cool down ==
    2 •       **Phase**               :       2 
    3 •       **Status**              :       Draft   
    4 •       **Category**            :       Daytime testing (functionality and operability) (C3)                           
    5 •       **Recurrence**  :       after instrument installation at telescope platform
    6 •       **Duration**            :       1 day
     1== P2.1 Basic functionality and shutdown procedure test, cryostat cooldown ==
     2
     3- **Phase**             :       2 
     4- **Status**            :       Draft   
     5- **Category**  :       Daytime testing (functionality and operability) (C3)                           
     6- **Recurrence**        :       once after instrument installation at telescope platform
     7- **Duration**  :       1 day
     8
    79**Description**
    8 •       Activating the instrument after the installation of SHARK-NIR at the telescope platform. Also, the shutdown procedure will be checked.
     10- Activating the instrument after the installation of SHARK-NIR at the telescope platform. Verification of the shutdown procedure.
     11
    912**Prerequisites**
    10 •       SHARK-NIR installed on the LBT telescope platform.
     13- SHARK-NIR is installed on the LBT telescope platform.
     14
    1115**Procedure**
    12 •       Switch on all the cabinets, follow the instrument telemetry and see if the telemetry is logging.
    13 •       Turn on all the hardware subsystems turned on and start all the corresponding services. Check all the logs from the services.
    14 •       Check the shutdown procedure (except the cryostat warm-up).
    15 •       Testing the electronics and SW rotation of the knob controlling the cool down process (LBTI side.)
    16 •       Cool down the cryostat
     16- Switch on all the cabinets, follow the instrument telemetry and see if the telemetry is logging.
     17- Turn all the hardware subsystems turned on and start all the corresponding services. Check all the logs from the services.
     18- Check the shutdown procedure (except the cryostat warm-up).
     19- Testing the electronics and SW rotation of the knob controlling the cool down process (LBTI side).
     20- Cooldown the cryostat.
     21
     22**Templates**
     23
    1724**Success criteria**
    18 •       Activating instrument successfully.
    19 •       All systems turned on and the services all running without any errors.
    20 * The shutdown procedure is checked and working as it should be.
    21 •       Cryostat cooling started and on-track.
     25- Activating instrument successfully.
     26- All systems are turned on, and the services are all running without any errors.
     27- The shutdown procedure is checked and working as it should be.
     28- Cryostat cooling started and is on track.
    2229
    2330**Notes**
    2431
    2532**LBTO support**
    26 •       Testing the working of the knob (motor/manual) controlling the cooldown.
    27 * Liquid Nitrogen fill
    28 * Vacuum pump
    29 **Associated SHARK-NIR personnel**
     33- Testing the working of the knob (motor or manual) controlling the cooldown.
     34- Liquid Nitrogen fill
     35- Vacuum pump
    3036
    3137**Date performed and by whom**
    32 
    33 **Comments**
    34 