wiki:docs/CommissioningPlan/P2.1

Version 14 (modified by kradhakrishnan, 3 years ago) (diff)

--

P2.1 Basic functionality and shutdown procedure test, cryostat cooldown

  • Phase : 2
  • Status : Draft
  • Category : Daytime testing (functionality and operability) (C3)
  • Recurrence : once after instrument installation at telescope platform
  • Duration : 1 day

Description

  • Activating the instrument after the installation of SHARK-NIR at the telescope platform. Verification of the shutdown procedure.

Prerequisites

  • SHARK-NIR is installed on the LBT telescope platform.

Procedure

  • Switch on all the cabinets, follow the instrument telemetry and see if the telemetry is logging.
  • Turn all the hardware subsystems turned on and start all the corresponding services. Check all the logs from the services.
  • Check the shutdown procedure (except the cryostat warm-up).
  • Testing the electronics and SW rotation of the knob controlling the cool down process (LBTI side).
  • Cooldown the cryostat.

Templates

Success criteria

  • Activating instrument successfully.
  • All systems are turned on, and the services are all running without any errors.
  • The shutdown procedure is checked and working as it should be.
  • Cryostat cooling started and is on track.

Notes

LBTO support

  • Testing the working of the knob (motor or manual) controlling the cooldown.
  • Liquid Nitrogen fill
  • Vacuum pump

Date performed and by whom