Version 14 (modified by kradhakrishnan, 3 years ago) (diff) |
---|
P2.1 Basic functionality and shutdown procedure test, cryostat cooldown
- Phase : 2
- Status : Draft
- Category : Daytime testing (functionality and operability) (C3)
- Recurrence : once after instrument installation at telescope platform
- Duration : 1 day
Description
- Activating the instrument after the installation of SHARK-NIR at the telescope platform. Verification of the shutdown procedure.
Prerequisites
- SHARK-NIR is installed on the LBT telescope platform.
Procedure
- Switch on all the cabinets, follow the instrument telemetry and see if the telemetry is logging.
- Turn all the hardware subsystems turned on and start all the corresponding services. Check all the logs from the services.
- Check the shutdown procedure (except the cryostat warm-up).
- Testing the electronics and SW rotation of the knob controlling the cool down process (LBTI side).
- Cooldown the cryostat.
Templates
Success criteria
- Activating instrument successfully.
- All systems are turned on, and the services are all running without any errors.
- The shutdown procedure is checked and working as it should be.
- Cryostat cooling started and is on track.
Notes
LBTO support
- Testing the working of the knob (motor or manual) controlling the cooldown.
- Liquid Nitrogen fill
- Vacuum pump
Date performed and by whom