P2.10 Test of all the remaining templates for sky observations

  • Phase : 2
  • Status : Draft
  • Category : Daytime testing (functionality and operability) (C3)
  • Recurrence : once after instrument installation at telescope platform
  • Duration : 2 days

Description

  • To verify all the (possible) remaining templates for sky observations, including testing the observing block template for a few specific configurations.

Prerequisites

  • Authorize SHARK-NIR on the SX side.

Procedure

  • Telescope static at Zenith

Templates

Success criteria

  • TBW

Notes

LBTO support

  • AO support

Date performed and by whom