    2 == P2.10        Cryostat warm up check  ==
    3 
    4 - **Phase**             :       1 
    5 - **Status**            :       Draft   
    6 - **Category**  :       Daytime testing (functionality and operability) (C3)
    7 - **Recurrence**        :       at the end of every SHARK-NIR run?
    8 - **Duration**  :       2 days
    9 
    10 **Description**
    11 - Checking the cryostat warming up procedure.
    12 
    13 **Prerequisites**
    14 - SHARK-NIR connected to LBT network.
    15 - Automatic logging of the cryostat temperature.
    16 
    17 **Procedure**
    18 - Run the cryostat warm-up sequence.
    19 - Check how the system is performing every 30 minutes.
    20 
    21 **Templates**
    22 
    23 **Success criteria**
    24 - Cryostat warmed up without any issues.
    25 - The temperature at the detector is stable at dome temperature.
    26 